25th Street Project

25th Street Project

STREET MARKING IS SCHEDULED FOR MONDAY JUNE 10, 2024.

Pending Rain Delays:

UPDATE:

Due to a break down at the blacktop plant and weather\rain, the timeline has changed.

Thursday June 6, 2024-Filling of gravel spots and potholes.

Friday June 7, 2024-Paving of roadway.

Saturday June 8, 2024-paving of approaches and alleys.

Black Top Milling will be done on Monday June 3rd and Tuesday June 4th, 2024.

Paving will be done Thursday June 6th and Friday June 7th, 2024.